North Torrance Well Field Phase II Design

The City of Torrance is upgrading its domestic water system with the North Torrance Well Field project. The project includes well numbers 1 and 10, an access road, utilities, a three-million gallon water tank, and a booster pump station at the Yukon site, located west of Yukon Elementary School in North Torrance.


CWE provided design services for the project’s second phase, including an access road, utility pipes, water main, concrete block yard, and most notably, a 48-inch overflow/storm drain to be installed using trenchless technology under I-405 that will connect to the existing County storm drain near West 182nd Street. CWE will also perform construction management for this project.